- Query
- Closed
- Range of the Standard:
- Available to other authorities
- Character of the query:
- Policy not
- Type of participation:
- Not normative projects
Summary
In accordance with articles 12 and 14 of the royal decree 337/2014, of 9 may, by approving the regulations on technical conditions and guarantees of safety high voltage power and its Follow-Up Technical InstructionsITC-RAT01-23, were adopted, by resolution of 16 may 2018 the directorate General for industry and small and medium enterprises, type the following projects:
- Draft substations type with conventional switchgear (132/30 kilovolts – 132 kV/20 – 55/12 kV – 30 kV/12). Code PT-SECO.01:
- Standard project with substations hybrid switchgear outdoors (132/30 kilovolts – 132 kV/20 – 55/12 kV) Code: PT-SEHI.01.
These Types reflected features that are substantially different from the current needs of this type of installation does not meet the objective for which were adopted, it is proposed that its cancellation.
Therefore, is submitted that proposal cancellation public hearing. Model projects whose cancellation is proposing are available on the following link
The rules of procedure of high-TensionRemission deadline
Deadline for submitting arguments until the day Thursday, October 5, 2023
Submission of allegations
The allegations may be sent to the email address: participacion_csegind@mincotur.es indicating in the subject: "Participación pública. Anulación Normas Particulares y Proyectos Tipo VIESGO_BEGASA" p>
In general the contributions received are considered likely to be made public. The parts of the information provided that, in the opinion of the person concerned, should be treated confidentially and consequently is not free dissemination, should be specifically identified in the text of the contribution, not to be regarded as the generic messages confidentiality of information.